Q&A Forum

Questions and Answers For:
IM 0292(93)76 - LSDC, Barrier, Joints, Appr Slabs - PCN - 092A
 
 The forum is now closed. No further questions or answers will be posted.
Please refer to the following link for rules and information regarding the Q&A Forum: Q&A Forum Information

The department may post questions and answers until 10:00 am CT on 2/17/2026 at which time the forum will be closed.




Date Submitted: 2/12/2026 11:44:08 AM Company: Journey Group Companies
Question #1
Is there traffic Control included in the project on I-29 for deck removal/bolt coring?
Answer Date Answered: 2/12/2026 2:48:13 PM
This issue will be addressed by addendum.