Questions and Answers For:
674110 ( ) - Water Main - PCN - X06V
The forum is now closed. No further questions or answers will be posted.
Please refer to the following link for rules and information regarding the Q&A Forum:
Q&A Forum Information
The department may post questions and answers until 10:00 am CT on 2/17/2026 at which time the forum will be closed.
| Date Submitted: |
1/29/2026 10:53:33 AM |
Company: |
BX CIVIL & CONSTRUCTION, INC. |
| Question #1 |
| Since the SDDOT DBE directory is currently down until further notice. What DBE directory are we to work off of to try to achieve the DBE Goals? |
| Answer |
Date Answered: |
1/29/2026 11:04:32 AM |
| All inquiries relative to the SRF documents and DBE requirements can be directed to Sam Sapkota, Natural Resources Engineer, Environmental Funding Program, Dept. of Agriculture & Natural Resources, Foss building, Pierre, SD (605)308-0157. Please also refer to the NOTICE TO CONTRACTORS for additional information. |
| Date Submitted: |
2/11/2026 3:20:50 PM |
Company: |
Core & Main |
| Question #2 |
| I'm looking to get some clarification on the domestic requirements for this project. I see in the special provisions that both SRF and AIS are mentioned, but I did not see any mention of "Buy America". Is "Buy America" going to be required? This is a determining factor on if hydrants and valves supplied for the project will need the body bolts to be domestic. If AIS is only required, valves and hydrants do not typically have domestic body bolts. |
| Answer |
Date Answered: |
2/12/2026 11:59:57 AM |
| Build America, Buy America Requirements do not apply to this project. |
| Date Submitted: |
2/11/2026 3:21:44 PM |
Company: |
Core & Main |
| Question #3 |
| Is 6'6" the bury depth that should be quoted for the hydrants? |
| Answer |
Date Answered: |
2/12/2026 11:58:36 AM |
| Hydrants shall be provided to allow for 6 feet of cover on the main and for the hydrant flange to be 2-4 inches above grade per the detail on sheet 17. |